Skip to content

Trusted Lighting Solutions Experts

QUICK SHIP205-323-4208
Linkedin page opens in new windowInstagram page opens in new windowPinterest page opens in new window


Lighting Solutions of Alabama
Trusted Lighting Solutions Experts
Lighting Solutions of Alabama
  • Home
  • Our Products
    • Northern Territory
    • Southern Territory
    • Mississippi Territory
  • Controls
  • Education
  • News & Events
  • Inspiration
    • Project Gallery
    • Videos
  • Resources
  • Our People
  • Home
  • Our Products
    • Northern Territory
    • Southern Territory
    • Mississippi Territory
  • Controls
  • Education
  • News & Events
  • Inspiration
    • Project Gallery
    • Videos
  • Resources
  • Our People

Start-up Visit Request Form

Step 1 of 5

20%
MM slash DD slash YYYY
Address
MM slash DD slash YYYY
General
  1. All panels, room controllers, switches, occupancy sensors, photocells, and other peripheral devices have been terminated and are powered.
  2. All RJ-45 CAT5/5E cables have been terminated and properly tested.
  3. All as-built documentation is complete, accurate and submitted to Lighting Solutions at least 2 weeks prior to the commissioning start-up date.
    The as-built information must include the following.
    • Panel/Room load schedules
    • Switch schedules
    • Occupancy sensor settings. Auto On/Off, Vacancy Only and time out
    • Daylight harvesting information
    • Time clock schedules
    • Any programming information that may be required for a fully functioning system.
  4. An electrician familiar with the installation of the lighting control system, must be available with ladders or anything else for access to the system components.
  5. Ensure that end user representatives are to be onsite for orientation and training on the system.
Daylighting Systems
  1. All daylighting sensors have been installed and fully operable.
  2. The daylighting control areas are completed and ready for occupancy.
Dimming Systems
  1. All dimming controllers have been terminated and are powered.
  2. All lighting fixtures have been installed and 0-10V dimming wires have been installed and verified.
Have questions?? Email those to [email protected]
Please confirm all of the following tasks are complete:(Required)
Start-up and training have been coordinated with the following parties:(Required)
Will training happen during the visit.(Required)
MM slash DD slash YYYY
Requested Training Time
:

NOTE: An additional charge may apply if training is not scheduled during the time of the start-up.

Is there anything else we should know?

Please read, sign and email to [email protected]

If the items are not completed, as verified above, on the arrival of the Field Engineer, then the Field Engineer will leave the job site and the contractor or distributor will be charged the full cost of the scheduled visit. Another visit will need to be rescheduled with Lighting Solutions at the contractor/distributor’s expense once all the above items have been completed.
Have questions?? Email those to [email protected]